The biggest mistake we see is underestimating structural and mechanical relocation costs. Homeowners often budget for demolition and drywall but forget about rerouting plumbing vents, relocating HVAC trunk lines, or upgrading electrical panels. In Arden, an open floor plan remodel cost in Las Vegas (2026) may typically fall into these ranges:
- Non-load-bearing wall removal with cosmetic updates: $8,000 – $20,000.
- Load-bearing wall removal with engineered beam: $25,000 – $60,000.
- Full kitchen-living reconfiguration with flooring, cabinets, and lighting: $60,000 – $120,000+.
One client planned for $40,000 to open a kitchen and living room. After discovering undersized existing footings, we had to pour new concrete pads to support LVL posts. That added excavation, inspection scheduling, and curing time – extending the project by three weeks. Typical timelines:
- Engineering and permits: 2 – 4 weeks.
- Demolition and framing: 1 – 3 weeks.
- Mechanical, electrical, drywall, finishes: 3 – 8 weeks.
Cost fluctuates based on three primary factors: site complexity, material costs, and total scope. Steel beams cost more than LVLs but may be required for longer spans. Custom cabinetry and wide-plank flooring increase finish budgets. For a deeper look at financial planning, review our
budgeting guide and insights from our
general contractor team. These figures are preliminary benchmarks for informational purposes only and do not constitute a binding quote. An on-site evaluation is required for a final proposal.